Audit and Risk Committee

Tuesday 18 February 2025 at 9:30 am

 

 

AGENDA

 

 


Audit and Risk Committee

18 February 2025

Audit and Risk Committee Agenda

 

Meeting to be held in the Council Chamber

36 Water Street, Whangārei

on Tuesday 18 February 2025, commencing at 9:30 am

 

Recommendations contained in the agenda are NOT decisions of the meeting. Please refer to minutes for resolutions.

 

MEMBERSHIP OF THE Audit and Risk Committee

 

Councillor John Blackwell

Councillor Joe Carr

Councillor Jack Craw

Councillor Peter-Lucas Jones

Ex-officio Councillor Geoff Crawford

Independent Tangata Whenua member George Riley

Independent Tangata Whenua member Dee-Ann Wolferstan

Independent Consultant Jonathan Eriksen

Independent Risk Advisor Steve Watene

 

 

 

KARAKIA / WHAKATAU

 

RĪMITI (ITEM)                                                                                                      Page

1.0      Ngā Mahi Whakapai/Housekeeping

2.0      Ngā Whakapahā/apologies   

3.0      Ngā Whakapuakanga/declarations of conflicts of interest

4.0      Ngā Whakaae Miniti / Confirmation of Minutes

4.1      Confirmation of Minutes - 18 November 2024                  4

5.0      Receipt of Action Sheet

5.1      Receipt of Action Sheet                                                       11

6.0      Reports

6.1      Election of a Chairperson for the 18 February 2025 Audit and Risk Committee meeting                                             14

6.2      Internal Audit Schedule Report                                          17

6.3      Fraud, Corruption and Dishonesty Activity Update        25

6.4      Quarterly report for Health and Safety performance - October to December 2024 period                                    35

6.5      Regulatory Services Quarterly Report                               40

6.6      RMA Compliance, Monitoring and Enforcement Framework                                                                             52

6.7      Financial Report to 31 January 2025                               189

6.8      Insurance Update                                                               195

7.0      Kaupapa ā Roto / Business with the Public Excluded         198

7.1      Confirmation of Confidential Minutes - 18 November 2024

7.2      Risk Management Activity Update

7.3      Report on Litigation and Enforcement 01 October - 31 December 2024

 

 


Audit and Risk Committee                                                                               item: 4.1

18 February 2025

 

TITLE:

Confirmation of Minutes - 18 November 2024

From:

Margaret Knight, PA to Group Manager Corporate Services

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Ngā mahi tūtohutia / Recommendation

That the minutes of the Audit, Risk and Finance Committee meeting held on 18 November 2024 be confirmed as a true and correct record and that these be duly authenticated with the Chair’s electronic signature.

 

Attachments/Ngā tapirihanga

Attachment 1: ARF Committee Minutes  

 

 


Audit and Risk Committee  ITEM: 4.1

18 February 2025Attachment 1

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

 

 


Audit and Risk Committee                                                                               item: 5.1

18 February 2025

 

TITLE:

Receipt of Action Sheet

From:

Margaret Knight, PA to Group Manager Corporate Services

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Whakarāpopototanga / Executive summary

The purpose of this report is to enable the meeting to receive the current action sheet.

 

Nga mahi tutohutia / Recommendation

That the action sheet be received.

 

Attachments/Ngā tapirihanga

Attachment 1: Action Sheet  

 

 


Audit and Risk Committee  ITEM: 5.1

18 February 2025Attachment 1


 

 


Audit and Risk Committee                                                                               item: 6.1

18 February 2025

 

TITLE:

Election of a Chairperson for the 18 February 2025 Audit and Risk Committee meeting

From:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 03 February 2025

 

Executive summary/Whakarāpopototanga

 

At the 10 December 2024 council meeting, the Chair of the Audit and Risk Committee was removed and it was resolved that council initiate a process to appoint an independent Chairperson to the Committee.  This appointment process has not been completed and therefore there is currently no Chair of the Audit and Risk Committee.  Furthermore, a Deputy Chair is not included in the Terms of Reference for this Committee.

 

Standing Order 14.1 stipulates that in the absence of the Chair, the Deputy Chair must preside, or the local authority members who were present must elect a member to be Chair at the meeting.

 

This report facilitates the election of a Chairperson for the 18 February 2025 Audit and Risk Committee meeting.

 

Recommendation(s)

1.        That the report ‘Election of a Chairperson for the 18 February 2025 Audit and Risk Committee meeting’ by Bruce Howse, Pou Taumatua – Group Manager Corporate Services and dated 31 January 2025, be received.

2.        That in the event more than one nomination for Chairperson is received, “System A” as specified in Clause 25 of Schedule 7 to the Local Government Act be used for the election of the Chairperson.

3.        That _______________________________ be elected the Chairperson for the 18 February 2025 Audit and Risk Committee meeting.

 

Background/Tuhinga

The Chief Executive Officer will call for nominations for election to the office of Chairperson.  A mover and seconder will be required for each nomination.  Any nomination that is moved but not seconded, will be deemed to have lapsed.

If only one nomination is received, that person will be declared to be elected.  Should more than one nomination be received, the council will be called upon to decide which of the two systems of voting (as specified in Clause 25 of Schedule 7 to the Local Government Act) is to be used to make the appointment.  The two systems are as follows:

System A

(a)      Requires that a person is elected or appointed if he or she receives the votes of a majority of the members of the local authority or committee present and voting; and

(b)      Has the following characteristics:

(i)        There is a first round of voting for all candidates; and

(ii)       If no candidate is successful in that round there is a second round of voting from which the candidate with the least votes in the first round is excluded; and

(iii)      If no candidate is successful in the second round there is a third; and if necessary a subsequent, round of voting from which, each time, the candidate with the fewest votes in the previous round is excluded; and

(iv)      In any round of voting, if two or more candidates tie for the lowest number of votes, the person excluded from the next round is resolved by lot.

System B

(a)  Requires that a person is elected or appointed if he or she receives more votes than any other candidate; and

(b)  Has the following characteristics:

(i)           There is only one round of voting; and

(ii)          If two or more candidates tie for the most votes, the tie is resolved by lot.

It should be noted that resolving by lot will be conducted by putting each person's name on the same size piece of paper and put in a box from which the name is drawn.

Considerations

 

1.        Options

No.

Option

Advantages

Disadvantages

1

System A

Carries a lesser likelihood that the Chairperson of council could be determined by lot.

More complex.

2

System B

Simple system

Carries a higher likelihood that the Chairperson of council could be determined by lot.

 

The staff’s recommended option is that, in the event more than one nomination be received for Chairperson, System A be applied.

2.        Significance and engagement

The committee must elect a Chairperson and therefore in relation to Section 79 of the Local Government Act 2002 and council policy, this issue is considered to be of low significance.

3.        Policy, risk management and legislative compliance

This report is submitted for consideration by the committee pursuant to the statutory requirements of Schedule 7 clause 26(6) of the Local Government Act 2002.

Being a purely administrative matter, Climate Impact, Environmental Impact, Community Views, Māori Impact Statement, Financial Implications and Implementation Issues are not applicable.

 

Attachments/Ngā tapirihanga

Nil

 

Authorised by Group Manager

Name

Bruce Howse, Pou Taumatua – Group Manager Corporate Services

Date

 

 

 

 


Audit and Risk Committee                                                                               item: 6.2

18 February 2025

 

TITLE:

Internal Audit Schedule Report

From:

Mandy Tepania, Audit and Assurance Lead

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Executive summary/Whakarāpopototanga

The internal audit schedule is provided in Table 1.  The schedule shows the timing for each internal audit item and a status update on progress. 

 

A proposed internal audit schedule for 2024/25 onwards is provided in Table 2.

 

An update on the Contract management Audit and next steps in the process.

 

An update on the Policy and Procedures Audit and the next phase of the project.

 

An Internal Audit Maturity Assessment update to support recommendation 3.

 

Recommendation(s)

1.        That the report ‘Internal Audit Schedule Report ’ by Mandy Tepania, Audit and Assurance Lead and dated 11 February 2025, be received.

2.        That the report ‘Internal Audit Schedule Report ’ by Mandy Tepania, Audit and Assurance Lead and dated 11 February 2025, be received.

3.        That the Audit and Risk Committee support the engagement of Deloitte NZ to carry out a re-assessment of council's internal audit maturity, following up on the original assessment by Deloitte in May 2022.

 

Options

 

No.

Option

Advantages

Disadvantages

1

Adopt the engagement of Deloitte NZ to carry out a re-assessment of council's internal audit maturity

Deloitte NZ completed the original assessment in 2022.

Fees associated with the assessment.

2

Do not adopt the engagement of Deloitte NZ in re-assessment of Council’s internal audit maturity

No fees.

Councils internal audit maturity assessment will remain at in its original state as assessed in 2022.

 

The staff’s recommended option is 1, to adopt the engagement of Deloitte NZ to carry out a re-assessment of council’s internal audit maturity.

Considerations

Being a purely administrative matter, climate impact, environmental impact, community views and Māori impact are not considered relevant.

1.    Financial implications

 

The Internal Audit Maturity re-assessment has been budgeted in the 2024/2025 financial year.

2.    Implementation issues

There are no anticipated implementation issues for the re-assessment of the Internal Audit assessment.

 

3.    Significance and engagement

In relation to section 79 of the Local Government Act 2002, this matter is considered to be of low significance when assessed against council’s significance and engagement policy because it relates to an administrative matter.  This does not mean that this matter is not of significance to tāngata whenua and/or individual communities, but that council is able to make decisions relating to this matter without undertaking further consultation or engagement.

4.    Policy, risk management and legislative compliance

 Support in having the re-assessment completed is consistent with the internal audit function, one aspect of the overall risk management framework as outlined by All of Government (AOG) Enterprise Risk Maturity Framework.

Background/Tuhinga

 

Key

Complete

Underway

Deferred

Not Started

Year

Item

Status

 

 

 

2024/2025

The Pathway Te Huarahi Tika Quality Review – New Quality program is underway across 22 different service delivery groups within NRC.

·    14 reviews completed.

·    8 reviews scheduled to be completed Q3/4.

2025

Local Government Act Section 17A Service Delivery Audits

·    Information Services and Technology due in 2025

2024

Internal Audit review on Infocouncil Agenda protocols

·    Decision made to develop a Confidentiality Policy to be delivered 2025

2024

Contract management Audit

·    Contract Management Audit now complete

·    External Peer Review

·    Scope and Schedule

·    Implementation and training package

2024

Policy and Procedures Audit – part of the delivery refresh program

·    New Policy Planform developed - Completed

·    Development of a controlled Policy Review Schedule

·    Ongoing policy review and management

·    Procedure review continues

·    Each procedure has a review date notification – review/approval or archive

2024

IT Systems and Software Audit

·    Collating a full list of software and services currently used at NRC. - Completed

·    Review of all software used to confirm fit for purpose and support a three-year improvement plan. -  Technology Working Group

2024/2025

Payroll audit to provide assurance surrounding relevant processes, controls, compliance with policy as well as provide some benchmarking against similar sized organisations and best practice.

·    External BDO Audit is complete

·    Draft report received for review

 

2025

Health and Safety Maturity Audit

·    External provider will complete the audit

·    Reviewing NRC H&S procedures and policies with a focus on the Health & Safety at Work Act (HSWA) 2015.

·    The audit will include contract management H&S requirements.

 

Table 2: Proposed internal audit schedule 2024/25 onwards.

Year

Item

Status

2025

Forest Management, audit of effectiveness of (outsourced) management, harvest schedule, health, and safety compliance, reporting etc.  Biodiversity audit is completed – implementation will be reviewed as part of the overall audit outcomes.

Currently on hold – future of the Forest is to be determined

2024/25

Internal Audit – NRC Firearms Officer will complete audit as per the Firearms Standing Operating Procedures (SOP)

Underway – Please see Deep Dive Report

2024

Audit – Risk and Assurance Program – progression with Risk Appetite and Maturity following the Deloitte assessment completed in May 2022

Planned Q3/4 2024

2024/25

Fraud Detection Review – External provider to review NRC current processes

Planned for June 2025 

2024/25

Financial Staff Benefit Policy Review – this review will include all policy relating to staff /councillor benefits/remuneration:  Credit card, Travel, Expenditure,

Planned for Q3/4 2025

2025

Procurement Management – Audit of current procedures, framework and training needs (Contract Management Audit – External Peer Review)

Planned for Q3/3 2025

2025

Integrity Analytics (Accounts Payable, Bank Payments, related parties, Sensitive expenditure and payroll) plus technology fee
External audit completed by Deloitte – Annual audit

Planned for Q4 2025 

2025

Internal Audit Maturity review
Risk – review of current system, engagement and reporting

Planned for Q3/4 2025

2024/25

Vehicle FBT – Audit on current use

Planned for Q3 2025

2025

Catering – Audit on consistency with Policy and procedures (Budget, approval)

Planned for Q3/4 2025

2025/2026

Annual Business Continuity Review – meeting with critical functioning services within NRC to ensure plans are up to date (contacts etc)

Planned for Q2 2026

2025

Business Continuity Review – Tabletop exercise

Planned Q3 2025

 

Contract Management Audit

 

Internal audit of contract management

 

A comprehensive internal audit of councils' contract management programme was carried out at the end of last year.  The audit sought to identify areas of risk, and opportunities for improvement.   Contract management across NRC is complex due to the very wide range and type of contracts required to support the work we do, with 633 contract files currently in council's contract management system.  

 

Audit findings

The audit identified a lack of systems (including software), processes, and training to support this level diversity and complexity, resulting in inadequate contract management and increased risk.

 

The audit found that existing templates, software, process and systems used to manage contracts across council are largely not fit-for-purpose and not well used.  The current system lacks tracking, monitoring, and reporting functions, with no link with payments in Tech 1 (financial system), or to risks, and no ability to create confidential contracts (resulting in workarounds).  There are duplications between the contract management and project management systems, and heavy reliance on staff self-management resulting in a high risk of human error; there are few checks on contract validity and completion. All templates and frameworks are in need of improvement.

 

Audit recommendations

The primary recommendation was that a contract management (software) solution be implemented to guide contract management at NRC.  This would need to be supported by the review and implementation of fit-for-purpose templates, process maps, and guidance material.  Closer monitoring and overview, including ensuring that contracts are seen through to completion then closed, was also advised.  It was suggested that this could be managed by way of a dedicated role, and/or by centralising contract management.

 

Next steps

Given the wide range of issues identified and the level of risk to council, external consultants (PWC) are being engaged to peer-review the internal audit and recommendations and provide advice on the next steps.  This will include prioritisation of the areas of highest risk, and identification of 'easy fixes' and best practice.  This is expected to occur during March - May this year.  Staff will then formalise an improvement plan.

 

It is expected that by June a clear schedule of improvements will be complete and implementation of improvements underway, and that the identification of software systems will be underway, or possibly complete if able to be incorporated in to Project Apollo.  

It is noted that the centralisation of contract management and the procurement of specific software will require resourcing, and that this may need to be included in the 2026/27 Annual Plan.  Several improvements should be able to be carried out in the meantime.

 

Policy and Procedures Audit

Procedures

Procedures managed through the Process Manager (PROMAPP) system are being reviewed weekly to ensure unpublished procedures are completed, approved and published within a 2 monthly timeframe. All users are being offered training in the program to ensure functionality is fully embraced and best practise is supported.

• Users (371) all staff have used the program in the last 6 months

• Procedures (830 in total – 162 unpublished – 320 need review)

Policy

A centrally managed register enabling a streamlined schedule of renewal to ensure all policies are reviewed in a timely manner consistent and controlled visibility to ensure latest versions are visible to all staff.

• Policy (69 to date)

• Not including frameworks, SOPs, Manuals, Plans, Strategy or standards as these are currently managed by the author

 

Non-policy documents, including SOPs

A programme of work is planned to scope, review, and set up a system to manage all non-policy documents, including SOPs, manuals, plans/strategies and standards.  This work forms part of the strategic delivery refresh programme (Shift 1 - towards greater focus on strategic outcomes and aligned operational delivery), and is scheduled to begin in March 2026, after all organisational policies have been brought up to date.  

The project will follow a similar format to the policy review, involving engagement with staff, establishment of issues, and development of a fit-for-purpose and centralised management system for these critical documents. Peer review and external advice will be used where considered necessary.

Internal Audit Maturity Assessment – Engagement of Deloitte NZ

Context/background:

In 2022 council commissioned Deloitte NZ to carry out an assessment of NRC's internal audit (IA) maturity and recommend improvements. The report was completed in May 2022, and placed NRC’s internal audit maturity at a level 2 of 5.  This level of maturity was considered to be in an acceptable range for a council of our size at the time.  Recommendations were made across four broad areas: 

·     Increased senior leadership engagement in IA and assurance activities 

·     Review and update the IA plan based on NRC’s key risks 

·     Adopt a risk-based approach to IA planning and activities 

·     Formalise the IA function and its role within the organisation 

Staff used the report to build an action plan that identified the need for change or improvement and set out clear actions to address these.  Steady progress has been made on this plan, with a suite of improvements implemented including changes to reporting lines and oversight, development and implementation of a new quality improvement system, and development of an internal audit framework.

With implementation of the improvement plan now well advanced, and with the growth that council has experienced, a re-assessment of internal audit is considered beneficial. The purpose of re-assessment is not to necessarily see a movement in NRCs internal audit maturity level, but to ensure that the actions planned and being carried out are the most effective and fit-for purpose to achieve a goal of continuous improvement.  

It is proposed to contract Deloitte to carry out this re-assessment.  As they are currently council's financial auditors, their engagement will require approval from OAG, and the approval of the Audit and Risk Committee.

Attachments/Ngā tapirihanga

Attachment 1: How to request a Policy - New or Amendment Procedure from PROMAPP  

 

 


Audit and Risk Committee  ITEM: 6.2

18 February 2025Attachment 1



 


Audit and Risk Committee                                                                               item: 6.3

18 February 2025

 

TITLE:

Fraud, Corruption and Dishonesty Activity Update

From:

Mandy Tepania, Audit and Assurance Lead

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Whakarāpopototanga / Executive summary

The Fraud Corruption and Dishonesty Update Report provides the current state and any updates since the last report.

 

Ngā mahi tūtohutia / Recommendation

That the report ‘Fraud, Corruption and Dishonesty Activity Update ’ by Mandy Tepania, Audit and Assurance Lead and dated 4 February 2025, be received.

 

Background/Tuhinga

As a public sector organisation, the council is entrusted with ratepayer funds and its staff consultants, volunteers, contractors, and elected members are expected to maintain public trust by exhibiting the highest standards of integrity and honesty throughout all council’s activities.

 

Definition: 

 

Fraud: -         Is an intentional and dishonest act involving deception or misrepresentation, to obtain or potentially obtain, an advantage for themselves or any other person/organisation.

 

Dishonesty: - An act (or omission) undertaken without the belief that there is consent or authority for doing the act (or omission).

 

Corruption: - Refers to a person in authority exploiting their position for personal gain (e.g., receive gifts or other benefits to perform part of an official function, or omitting to perform an official duty resulting in personal gain for another).

 

A policy provides the outline to staff when reporting dishonest behavior to the Fraud Limitations Officer (FLO).  The below procedure outlines the steps taken.

 

A diagram of a company

Description automatically generated

 

This report provides several summaries:

 

·    Chart below provides a quick view of the 12 Fraud, Corruption and Dishonesty Risks Inherent/Residual controls in Table 1.

·    Fraud Corruption and Dishonesty Risk Register including treatments/controls in place as identified in Table 2.

·    Risk Management Matrix Evaluation Tool (ranking) Inherent/Residual Table 3.

 

Table 1. Report showing all Fraud Corruption and Dishonesty Risks scores (Inherent/Residual)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Table 2.  Fraud Corruption and Dishonesty Risk Register current rating and controls.

 

Risks below are identified in the risk register as ongoing risks with controls in place to manage and monitor any breach in behaviours.  All risks on this register have been reported including a brief overview of the controls in place for each.  Risk ratings are adjusted when a regular review identifies and requires a policy or process change be made to remove or limit chances of fraudulent, corrupt or dishonest behaviours.

 

Inherent Rating

Extreme

High

Moderate

Low

Residual Rating

Extreme

High

Moderate

Low

#

 

Risk Statement

Inherent Rating

Residual Rating

1: R00085

Data Loss through theft, unauthorized access, or distribution

9

6

Controls

Processes and policies in place, automatic PC screen lock, staff education, laptops for offsite work with security controls

2: R00112

Theft and inappropriate use of council assets

 

6

4

Controls

Vehicle inventory checks (current & sold), regular stock takes, lockable storage, disposal of assets by public auction, restricted and monitored access to building, user reporting (internet, cell phones) Treasury management policy monthly performance reporting, BP fuel reporting

3: R00117

Conflict of Interest

 

9

6

Controls

Staff annual declaration of interests, tendering process requires disclosure, segregation of duties, minutes of meetings declaration of any conflict of interest, employment application forms include questions.

4: R00115

Supplier Invoice Fraud

6

4

 

Controls

Delegation limits and authoristion process in place, ducal signatory procedure to release payments, segregation of duties in payment process, monthly actual vs budget reporting and review

5: R00121

Bribery and inappropriate receipt of gifts & secondary employment

6

4

Controls

Gift register reported to independent member of Audit & Risk subcommittee, Annual declaration of conflict of interest performed and report to CEO, external audit, employment contract in place for all staff, application form asks if they continue with any other employment and if there is any conflicts of interest before commencing with employment

6: R00106

Fraud Corruption and Dishonesty

 

10

5

Controls

Raise awareness through policy, provide fraud dishonesty and corruption training to staff including positions susceptible to such activities eg. ELT, DLT, managers, business supports and staff,

Misstatement of financial statements, maintain appropriate levels of insurance, investigate and implement any internal/external audit recommendations promptly, Policy and Procedures for reporting and investigating any items reported, Policy and Procedure regular review (e.g. Fraud, Dishonesty and corruption policy, Protected Disclosures Policy, Code of Conduct Policy)

7: R00118

Recruitment Fraud

 

6

4

Controls

Police checks for all new employees, checking qualification documents, completed application questionnaires are checked, psychometric testing where requested, credit checks perform on new employees where appropriate (e.g. finance)

8: R00119

Theft of Bus Service Revenue

 

6

4

Controls

Monthly reconciliations, restricted access, Internal audits

9: R00114

Timesheet and expense claim fraud

 

6

4

Controls

Monthly budget monitoring, authorisation process and workflow, police checks obtained where necessary, timesheets, sickness, other leave signed off by manager, internal audit where appropriate

10: R00120

Material misstatement of the financial statements

 

6

3

Controls

Internal/ external audits, segregation of duties and sign off processes

11: R00113

Payroll Fraud

 

3

2

Controls

Monthly budget monitoring, payment run audit reports reviewed and verified separately from payroll function, payment run variance report (compare previous to current and verify differences), segregation of duties payroll processing and authorisation process, data matching processes over bank account details, CAAT are performed annually, Review by HR/ELT of staff on payroll

12: R00116

Koha Fraud

 

3

2

Controls

Approval, receipting and confirmation process in place and reviewed and updated regularly

 

Table 3.  Risk Management Matrix Evaluation Tool (to explain the ranking) Inherent/ Residual

 

 

 

Likelihood

Consequence

Inconsequential (1)

Minor (2)

Moderate (3)

Major (4)

Severe (5)

Frequent (5)

5

Moderate

10

High

15

Extreme

20

Extreme

25

Extreme

Often (4)

4

Low

8

High

12

High

16

Extreme

20

Extreme

Likely (3)

3

Low

6

Moderate

9

High

12

High

15

Extreme

Possible (2)

2

Low

4

Low

6

Moderate

8

High

10

High

Rare (1)

1

Low

2

Low

3

Low

4

Low

5

Moderate

 

Fraud Limitations Officer updates:

I confirm that our current, and only active, fraud investigation has been completed.

The investigation confirmed the following actions:

The requirements for voluntary disclosure of relationships that may present a situation where a conflict-of-interest may exist, were not followed by the staff member.

Incorrect declarations were made by the staff member, by omission.

The actions were determined to not have been undertaken with an intent to gain financial advantage at the expense of the organisation and so the actions did not meet a reasonable threshold to substantiate fraud or dishonesty.

Disciplinary action has been undertaken and the matter is now closed.

 

Attached is the current ‘Manage conflict of Interest’ procedure for staff, updated annually by People and Culture (P&C).

A further review for the ‘Annual Declaration of Compliance’ process managed by P&C is underway.  Considering the outcomes from the investigation and feedback received from staff relating to the size and language of these declarations, a better approach is being sought, to ensure staff more fully understand their ongoing responsibilities and consequences on completion.

Current process:

1.    Annual declaration of compliance process launch (review, comms through Aotahi, CEO all staffer, Monthly Managers symposium plug, all managers emails etc).

2.    All staff complete declaration of compliance and conflict of interest submissions

3.    P&C report on completions (following deadline)

4.    Follow up with Employees and Managers not completed

5.    Follow up with GMs on the employees in their groups that have still not completed

6.    Final follow up – list to CEO on employees that have not completed

7.    An annual audit is completed (Integrity Analytics, Related Parties) comparing vendor to Employee, Vendor to Vendor and Vendor to Next of Kin to highlight any conflicts.

 

Attachments/Ngā tapirihanga

Attachment 1: Fraud Corruption and Dishonesty Risk Report Feb 2025

Attachment 2: Manage Conflict of Interest Procedure (PROMAPP)  

 

 


Audit and Risk Committee  ITEM: 6.3

18 February 2025Attachment 1


 


Audit and Risk Committee  ITEM: 6.3

18 February 2025Attachment 2



 


Audit and Risk Committee                                                                               item: 6.4

18 February 2025

 

TITLE:

Quarterly report for Health and Safety performance - October to December 2024 period

From:

Tamsin Sutherland, Health and Safety Advisor

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Whakarāpopototanga / Executive summary

This report is to inform the committee of the activity in Health and Safety for the period October to December 2024.   

An overview/summary of the report includes: 

·          A summary of the events, investigations and outcomes that have occurred in this period.

·          Health and safety training has continued to be a priority in this period.

·          A new health and safety management programme (Safety Champion) started a phased implementation on 7 October 2024. Initial feedback is that this transition is going well.

 

Ngā mahi tūtohutia / Recommendation

That the report ‘Quarterly report for Health and Safety performance - October to December 2024 period’ by Tamsin Sutherland, Health and Safety Advisor and dated 24 January 2025, be received.

 

Background/Tuhinga

1.        Health and safety performance

A summary of the health and safety performance for the period October to December 2024 is shown in Table 1 below:

·    A Location Compliance Certificate has been obtained for the Union East Street location. A detailed review of hazardous substance storage has been undertaken in readiness for the uploading of information to the new system Safety Champion. To ensure compliance with the regulations, staff training for emergency scenarios was improved. There is still work to be done on ensuring that all staff are familiar with the hazards associated with all products they may come into contact with. Health and safety inductions at Union East Street are being conducted for staff, 45 have been completed to date. Monthly site inspections will be carried out by the health and safety team to ensure ongoing compliance with the conditions of the location compliance certificate.

 

·    Health and safety training undertaken in this period includes first aid, 4WD and LUV and defensive driver skills, dog safety, de-escalation skills for conflict, contractor management, working at heights, fire safety training and wader training. Managers have confirmed that all field staff hold requisite training to complete field work. More structured H&S training was provided to interns and summer casual staff to ensure that these less experienced workers were better prepared for field work.

·    Incident reporting has risen again this quarter, as expected as field work increased. The transition to reporting in Safety Champion appears well received and has not created any barrier to reporting.

 

·    Safety Champion, the new software system for health and safety was launched on 7 October 2024. This programme is currently recording incidents/accident reports. Information on all hazardous substances held by NRC is currently being uploaded and will go live in February 2025.

 

A screenshot of a document

Description automatically generated

Table 1: Health and safety performance lead and lag indicators July to December 2024

Deep dive update

A programme of deep dive reviews by ELT members of the critical risks was established in 2024. This was intended to ensure that ELT are aware of the health and safety issues facing staff in their day to day work. The programmed assigned critical risks to the members of ELT for review. The programme was not completed within 2024 due to a combination of resourcing constraints (workload for ELT) and difficulty in identifying suitable unplanned critical risk exposure – aggressive people and psychosocial harm. The deep dives that were conducted provided valuable insights for ELT and were very well received by staff. This programme will continue through 2025, with priority given to the deep dives which were not completed before the end of 2024.

Health monitoring

Health monitoring was completed for all Whangarei field-staff who were due – 82 staff completed health monitoring and received immunisations relevant to their role.

Aggressive people

The Capturing Images, Footage and Audio Policy has been adopted. This provides staff with more clarity on using body cameras during visits enforcement visits. The intent is that the use of body cameras will deter aggressive behaviour towards Council staff. The increase of abuse and threats to staff is a sector wide issue. There were seven incidents where staff were threatened by aggressive people in this quarter, two of these were phone interactions.

Lone worker protection

A health and safety project team worked with Data Science and GIS to develop forms which identify where staff are working, which high risks activities are being carried out, and to provide an advanced way for managers to track staff safety in the field. The NRC GIS team submitted an application to the ALGIM Awards based on a recommendation from the Health and Safety Auditor, who highly commended the system. The system won the category for GIS Project of the Year.

 

2.           Injuries, incident and hazards

The most frequent incident type for the October to December 2024 quarter was vehicle overspeed reports. Although the most frequent incident for the quarter, the number of these incidents remains significantly lower than it was prior to the implementation of speed management reporting in February 2023. The number of contractor incident reports has risen as contract managers stress the importance of reporting incidents to NRC, however, this still indicates significant under reporting. In 2024 Council held 115 contracts with 82 vendors. A total of 22 incident reports relating to contract work were received.

A graph of a number of incident reported

Description automatically generated

Figure 1: Health and safety event reports categorised by type for the October to December 2024 quarter
 – note vehicle incidents include near misses whilst driving but not vehicle overspeed

 

In transition a further seven incidents were reported in the previous reporting system, bringing the total incident reports for the quarter to 90. Driving incidents include near misses, where NRC staff have had to take evasive action to avoid other road users. In two incidents this quarter, this resulted in staff leaving the carriageway to avoid another vehicle on the wrong side of the road. Staff are reporting that the defensive driver training has been very helpful in driving with greater awareness.

Every incident report is investigated to determine what can be learned, and what can be done more safely. The “hierarchy of controls” assigns are order of best mitigation (eliminating the hazard) to less effective, creating a safer system of work that relies on staff using PPE effectively. The outcome of the investigations undertaken in this quarter shows the outcomes identified in Figure 2 below.

Staff reported 23 near misses and seven new hazards this quarter. This proactive reporting is encouraging.

Figure 2: the highest level of control applied to the hazard identified in the reported incident at the outcome of the incident investigation.

In the investigations where ‘no controls’ were added this indicates that existing controls are already appropriate, however, some incidents such as slips, trips and falls will always occur working in a dynamic field environment.

 

3.           Events reported

90 incidents were reported in this quarter, compared to 55 in the previous quarter.

15 overspeed events were identified in ERoad for this period, plus two speeding tickets.  NRC vehicles travel in excess of 100,000kms in a typical month. The number of incidents recorded represents an average of one speeding event per 28,080 kms driven this quarter. Speed limit changes on beaches have been implemented, but district councils improving communication of the limits to drivers on beaches is still in progress. NRC is taking an educative approach for staff where speed limits are not yet posted at the beach.

One minor injury report required a small change to a bracket which had caused a cut to a member of staff. When this incident was raised, multiple other staff members also reported they had received cuts/scratches from this bracket, but had not reported it. This example shows there is evidently still an issue with under reporting of incidents.

 

4.           Events of interest

Note: the events of interest only detail high risk events, or events which affect large groups of people.

The following events are events of interest from the quarter October to December 2024:

Contractor incidents:

Aggressive person confronted contractor at managed forestry block whilst trespassing for unapproved hunting.

NRC staff incidents:

·    Discomfort from workstations are addressed on an ongoing basis.  Deskalators are routinely provided as a lower cost alternative to a standing desk when the need for a modified work station is identified. Deskalators create other issues for desk use, and are a cost compromise compared to standing desks.

·    10 incidents of minor cuts to hands through implements and on sharp objects in the environment

·    There were seven aggressive person incidents where landowners or members of the public confronted staff during their work.

·    There were three incidents of loads coming loose during transport within 21 vehicle reports.

·    Two incident reports related to the building not being adequately secured at the end of the work day.

 

5.           H&S Strategy work programme

Due to delays in the customisation build of Safety Champion, the health and safety team are behind the planned progress for implementation in some areas of the H&S Strategy.

·    Safety Champion has some ability to track staff training for competency components. It may be more appropriate to use a bespoke HR package to perform this function, this is being investigated.

·    Reporting from Safety Champion allows real time interrogation of incident/accident reports, and action outcomes by managers for their teams. This has improved the visibility of incident investigations for managers.

·    Fixed term project support for the transition to Safety Champion has been appointed, which will allow the transition to Safety Champion to continue without impacting the H&S Advisor roles.

 

6.           Legislation updates

The Health and Safety at Work Act 2015 is currently under review, consultation has closed. There is no date currently set for the outcome of this review to be published.

The Code of Practice for Temporary Traffic Management has been withdrawn and new guidance, the New Zealand Guide to Temporary Traffic Management has been issued. The new scheme is risk based and will allow a more nuanced approach to working in the road corridor. It can require less stringent conditions for work on very low volume roads, it will have little impact to the requirements for work on major roads. It does require NRC to identify any work that can be done in a different way, instead of exposing pedestrian-workers to work in the road corridor. Training will remain essential for staff.

 

Attachments/Ngā tapirihanga

Nil

 

 


Audit and Risk Committee                                                                               item: 6.5

18 February 2025

 

TITLE:

Regulatory Services Quarterly Report

From:

Colin Dall, Pou Whakaritenga - Group Manager Regulatory Services

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Whakarāpopototanga / Executive summary

This report covers the council’s consent processing and compliance monitoring functions/activities for the period 1 October to 31 December 2024.  A separate report on formal enforcement activities is included in the Confidential section of this committee agenda.

 

The following is a high-level summary of our consent application processing and compliance monitoring functions/activities during the reporting period:

Consents

Metric

October 2024

November 2024

December 2024

Total

Applications received1

39

44

32

115

Decisions issued2

79

84

101

264

Outside timeframes

0

0

0

0

Hearings

0

0

0

53

Objections/appeals

0

0

0

44

1     An application may include multiple activities which individually require a resource consent.

2     The number of decisions issued is based on the total number of activities that required a resource consent.

3     Two of the five hearings started in the previous financial year but finished in the current financial year.

4     There is also an appeal that had not been resolved that was lodged prior to 1 July 2023.

Of the applications in progress at the end of December 2024, 30 were received more than 12 months ago (four less than the previous reporting period).

Compliance Monitoring Events

Classification

Total

Full Compliance

Low Risk Non-compliance

Moderate Non-compliance

Significant Non- compliance

Air Discharge

42

41

1

0

0

Bore Consent

24

19

5

0

0

Coastal Discharge

42

32

3

7

0

Coastal Permit

160

131

26

3

0

FDE Discharge Permit

233

145

0

76

12

FDE Permitted Activity

66

49

0

14

3

Land Discharge

172

134

23

14

1

Land Use Consent

152

147

5

0

0

NES-CF

5

0

0

5

0

Water Discharge

129

74

21

30

4

Water Permit

83

79

1

3

0

Water Take

336

207

102

27

0

Period Total

1444

1058

187

179

20

Percentage

 

73.3

12.9

12.4

1.4

2024/25 Total

3347

2562

361

362

62

Percentage

 

76.5

10.8

10.8

1.9

 

Environmental Incidents

A total of 237 environmental incidents were recorded and investigated in the reporting period (84 in October, 73 in November and 80 in December).  The following graph compares the number of environment incidents investigated for each main incident category with the mean (average) number of incidents investigated for the same category and reporting period for the previous 10-year period.  The colour coding for the incidents investigated in the current reporting period gives the assessed scale of adverse effects of the incident.

 

Ngā mahi tūtohutia / Recommendation

That the report ‘Regulatory Services Quarterly Report’ by Colin Dall, Pou Whakaritenga - Group Manager Regulatory Services and dated 11 February 2025, be received.

 

Background/Tuhinga

 

Compliance ratings specified in this report are those recommended by the Ministry for the Environment’s “Best Practice Guidelines for Compliance, Monitoring and Enforcement under the Resource Management Act 1991” (2018):

Compliance grade

FULL COMPLIANCE with all relevant consent conditions, plan rules, regulations, and national environmental standards.

LOW RISK NON-COMPLIANCE. Compliance with most of the relevant consent conditions, plan rules, regulations, and national environmental standards. Non-compliance carries a low risk of adverse environmental effects or is technical in nature (e.g. failure to submit a monitoring report).

MODERATE NON-COMPLIANCE. Non-compliance with some of the relevant consent conditions, plan rules, regulations, and national environmental standards, where there are some environmental consequences and/or there is a moderate risk of adverse environmental effects.

SIGNIFICANT NON-COMPLIANCE. Non-compliance with many of the relevant consent conditions, plan rules, regulations, and national environmental standards, where there are significant environmental consequences and/or a high risk of adverse environmental effects.

 

 

 

Table 1:       Applications Received 1 October to 31 December 2024

IRIS ID

Consents Required

Received Date

Applicant

Description

APP.046137.01

1

1/10/2024

Island Getaway Limited

New 4-ton swing mooring in Matawuwhi Bay. Proposed mooring is outside of the Mooring Zone.

APP.046138.01

1

1/10/2024

Salt Air Limited

New 4-ton swing mooring in Matawuwhi Bay, Bay of Islands.

APP.037581.01

2

2/10/2024

Hylands Ancient Kauri Limited

Replacement consents for discharges associated with a commercial wastewater treatment system at 505 Kerikeri Road, Kerikeri.

APP.046142.01

3

2/10/2024

Waiharara Hall Society Incorporated

Bore for domestic use at 31 Kaimaumau Road, Waiharara.

APP.046146.01

1

2/10/2024

Poroti School Board of Trustees

Earthworks for flood remediation at Poroti School at 673 Mangakahia Road, Poroti.

APP.002478.01

1

3/10/2024

Far North District Council

Take groundwater from five bores for public water supply purposes for Kawakawa

APP.046147.01

1

3/10/2024

Far North District Council

Discharge off spec treated water via stormwater network to land at 149 Pukepoto Road, Kaitaia

APP.046172.01

3

3/10/2024

Whangarei District Council - Waste & Drainage

Earthworks to construct a flood pump at Rawhiti Street, Whangarei

APP.046134.01

1

7/10/2024

WDC

Construction of a roundabout on, and adajcent to, SH 1, Springs Flat

APP.046152.01

3

7/10/2024

Maarten Paul Groeneveld and Natsuko Kameoka

Bore for domestic, stock and irrigation use at 3615 Horeke Road, Taheke

APP.046153.01

3

7/10/2024

David Alexander Gillett And Maria Alejandra Laxalde Novoa

Bore construction for domestic and stock use at 545 Wiora Road, Kerikeri

APP.046154.01

3

7/10/2024

Shane Vincent Horan

Bore for domestic use at 174A Houhora Heads Road, Kaitaia

APP.008964.01

4

10/10/2024

Kaipara District Council

To excavate sand from a foredune and beach locations at Baylys Beach, includes stream works and hard protection. Replacement of activities associated with AUT.044351

APP.037324.01

1

11/10/2024

Valentina Grigorevna Rondova

Replacement consent for discharge of domestic wastewater at 12 Jean Millington Lane, Maunu, Whangarei Deemed to be a permitted activity AUT.202577.01.01

APP.037337.01

2

11/10/2024

Guy Royce & Ann Denise Austin

Replacement consent to discharge domestic wastewater at 23 Ngunguru Heights Rise, Ngunguru

APP.046160.01

3

14/10/2024

Brandon Kyle Ralph & June Keitha & Danny Cherrington

Bore construction at 3070 State Highway 1, Waiharara

APP.046165.01

4

15/10/2024

Maunugold Limited

Subdivision works at 9-11 Cemetery Road, Maunu, Whangarei

APP.037327.01

1

16/10/2024

Neil Dawson & Raewyn Anne Newman

Replacement consent to discharge secondary treated domestic wastewater from Lot 7 at 25 Jean Millington Road, Maunu, Whangarei

APP.046168.01

1

16/10/2024

Cherished Pets Cremation Services NZ Limited

Discharge to air associated with a pet cremator at 140A Ngunguru Ford Road, Kiripaka

APP.046176.01

2

22/10/2024

Far North District Council

Discharges associated with a waste transfer station at 2 Enterprise Street, Kaikohe

APP.046177.01

1

22/10/2024

Te Aupouri Commercial Development Limited

Short term groundwater take at Salvation Road, Pukenui to fill a reservoir

APP.046131.01

1

23/10/2024

Harbourside Boat Works Limited

Discharges associated with a boat maintenance facility at 346 Port Road, Whangarei

APP.046178.01

4

23/10/2024

J Spiers

Retrospective consents for works in and around a wetland at 195 Ladore Road, Okaihau

APP.046179.01

3

23/10/2024

Far North District Council

Earthworks and associated activities for a stormwater network upgrade at multiple sites at Moerewa

APP.037602.01

2

24/10/2024

Mark Andrew & Denise Barnes

Replacement consent to discharge wastewater to land at 11 Marine Vista Heights, Tutukaka

APP.046182.01

3

25/10/2024

Tararua Wind Power Limited

Earthworks and associated activities for roading upgrades at Maitahi Road, Babylon Coast Road, State Highway 12 and State Highway 14 for transporting components to the Kaiwaikawe Wind Farm.

APP.046183.01

4

25/10/2024

Far North District Council

Earthworks to install WW main in flood zone at 5 Eden Terrace, 19 Bank Street to 3 Bonnett Road, Kaitaia.

APP.004387.01

1

31/10/2024

Mangawhai Beach Hideaway Park &  H and H Foote & N Foote

Groundwater take for camping ground, Mangawhai Heads

APP.046184.01

3

31/10/2024

Mangapuriri Estate Limited

Works near a wetland at 574 Browns Road, Mangawhai

APP.046188.01

3

4/11/2024

Patrick James Dudley & Paula Slater

Bore construction at 1487 State Highway 1, Ohaihau

APP.046196.01

3

4/11/2024

Lodestone Energy Limited

Earthworks and associated activities for a solar farm at Hoanga Road and Danks Road, Dargaville

APP.019289.01

1

5/11/2024

Quail Ridge Country Club Limited

S127 change to site layout and disposal areas at Quail Ridge Country Club, Kerikeri

APP.046203.01

2

6/11/2024

Pare Rawiri Trust & M Taraeka

Wastewater discharge for papakainga at Kaitaia-Awaroa Road, Herekino

APP.046205.01

3

6/11/2024

The Salvation Army New Zealand Trust

Earthworks and associated activities for site development works in a flood hazard area at 36 North Park Drive, Kaitaia

APP.046208.01

3

6/11/2024

Edward Ross Smyth

Site development works in a flood hazard zone at 45 Windsor Way, Mangawhai

APP.005059.07

1

7/11/2024

Golden Bay Cement

S127 change to allow Refuse Derived Fuel (RDF) to be used as a fuel at Portland Cement Works, Whangarei

APP.046010.01

1

7/11/2024

David Milne & Margot Edwards

Jetty and associated rock groyne in the coastal marine area adjacent to 5 Moir Street, Mangawhai

APP.046209.01

1

7/11/2024

Northpower Limited

Works near wetlands at McKinley Road, Ruawai and Tikinui Slip Road, Te Kopuru associated with submarine cable replacement.

APP.002312.01

1

8/11/2024

Te Kihi Trust, Doubtless Trust, D P & P D Vendt, J G & G S Harrington & G Smith

Replacement consent to take water from a bore in the catchment of the Wheki Stream at Maungatapere

APP.046210.01

2

8/11/2024

Cornerstone Assets Limited

Discharge wastewater from a retail showroom and dwelling at 553 Kerikeri Road, Kerikeri

APP.046213.01

3

11/11/2024

NZTA - Waka Kotahi

Scour protection works in the bed of a stream Waiomio Stream, SH1, Waiomio

APP.046215.01

3

11/11/2024

Pukenui School Board of Trustees’

Bore construction for domestic and community supply at 35 Lamb Road Pukenui

APP.046216.01

3

11/11/2024

Adam Franklin & Janette Lindsay Neilson

Bore construction at 17 Edmonds Road, Kerikeri

APP.046218.01

1

12/11/2024

Wairahi Tracks Charitable Trust

Construct a shared path adjoining to, and within, a gumland wetland, 1411 and 1441 Cove Road, Mangawhai

APP.046220.01

1

12/11/2024

Northland Regional Council

Flood protection works at Wainui Valley Road, Wainui

APP.046221.01

1

12/11/2024

Northland Regional Council

Flood protection works in Te Ngaere

APP.046164.01

1

13/11/2024

Mr Christopher John Morris

Unauthorised structure in the coastal marine area adjacent to 65A Fosters Road, Mangonui

APP.046222.01

1

13/11/2024

P Cullinan

Earthworks in a flood zone at 106 Moir Street, Mangawhai

APP.046224.01

1

13/11/2024

Kauri Ruakaka Limited

Construction of a solar farm at 597 Port Marsden Highway, Ruakaka

APP.046225.01

2

14/11/2024

Summit Forests New Zealand Limited

Vegetation clearance at in the Honeymoon Forest located off Dutton Road, Peria

APP.046226.01

3

14/11/2024

Vitali Farm Company Limited

Earthworks within 10m of a natural wetland at 1509 Tinopai Road, Tinopai

APP.046227.01

3

14/11/2024

Taurima Taumata Limited

Bore construction for domestic use at McAdam Road, Waipu

APP.046235.01

1

18/11/2024

Fletcher Concrete & Infrastructure Limited

Take groundwater for commercial purposes at 6 Moir Point Road, Mangawhai Heads

APP.046236.01

1

18/11/2024

Cindy Jane Linder & Troy William Dawson

Take water from Awanui River for irrigation at 862 Gill Road, Kaitaia

APP.046237.01

3

19/11/2024

Noro Investments Lmited

Bore construction for domestic and stock use at St Marys Road, Waipu

APP.012962.01

2

20/11/2024

Muriwhenua Incorporation

Replacement consents for a marine farm and associated activities in Parengarenga Harbour (Ex Lease # 177)

APP.046240.01

1

20/11/2024

Northland Regional Council

Flood protection works at Mangamuka Marae, Iwitaua Road/State Highway 10, Mangamuka

APP.037325.01

1

21/11/2024

Christine Mary McDonald

Discharge secondary treated domestic wastewater to land at 16 Jean Millington Lane, Maunu.

APP.046241.01

1

21/11/2024

KiwiRail Holdings Limited

Works for stormwater drainage upgrade for flood protection south of Wahamiti Lane, Moerewa

APP.006153.02

1

22/11/2024

Hautope Trust & JID Rouse & SR King & BI Francis

S125 extension of lapse period to alter and extend a boat shed facility in the coastal marine area in Hatea River adjacent to Riverside Drive, Whangarei

APP.006154.02

1

22/11/2024

Hautope Trust & JID Rouse & SR King & BI Francis

S125 extension of lapse period to alter and extend a boat shed facility in the coastal marine area in Hatea River adjacent to Riverside Drive, Whangarei

APP.046250.01

2

25/11/2024

New Zealand Transport Agency - Waka Kotahi

Retrospective consent for emergency works between Piroa Stream Bridge and the intersection with Artillery Road, State Highway 1, Brynderwyn

APP.046251.01

1

25/11/2024

Fonterra Co-operative Group Limited

Take water from an unnamed wetland for use at the Maungaturoto dairy manufacturing site at Hurndall Street (State Highway 12), Maungaturoto

APP.046252.01

2

26/11/2024

Solid Production Limited

Discharge silage leachate to land from concrete pad at 147 Otakairangi Road, Riponui

APP.005424.01

4

27/11/2024

Kingfish Lodge 2016 Limited

Replacement consent for structures in the coastal marine area in Whangaroa Harbour

APP.011294.01

1

28/11/2024

Mangawhai Heads Management Limited

Discharge treated w/w to land at Mangawhai.

APP.007082.01

1

29/11/2024

First Blast 2020 Limited

Discharge contaminants to air at Port Road

APP.007145.01

1

29/11/2024

Whangarei District Council - Waste & Drainage

Discharge refuse and residual leachate to ground at Pohe Island closed Landfill.

APP.046259.01

1

29/11/2024

Baxter Family Trust and KO Baxter

Retrospective application for culvert installation which does not meet fish passage rules at 500 Waimate North Road and 39 Montrose Road, Kerikeri

APP.046264.01

1

29/11/2024

Pehiaweri B1B Ahu Whenua Trust

Papakainga development at 109 Ngunguru Road, Glenbervie

APP.010934.02

1

2/12/2024

Far North Holdings Limited

Early replacement of resource consents for Opua Wharf, Bay of Islands

APP.046265.01

1

3/12/2024

Meridian Energy Limited

Take groundwater at Rama Road, Ruakaka

APP.006818.01

1

4/12/2024

Avoca Lime Company (2010) Limited

To remove and place overburden, extract rock, and divert and discharge stormwater from a quarry, at Lovells Rd, Ruatangata West.

APP.042368.01

3

4/12/2024

Te Runanga O Whaingaroa

S127 change to earthworks for subdivision development at Ash Grove Circle, Haruru

APP.046272.01

1

9/12/2024

Whangarei District Council - Roading

Bridge over Waitaua Stream, Gillingham Road, Tikipunga

APP.046271.01

1

10/12/2024

Far North District Council

Coastal structures, earthworks, vegetation clearance to re-establish a section of the Pou Herenga Tai Twin Coast Cycle Trail, extending from Taumārere to Ōpua Cycle.

APP.007246.01

1

11/12/2024

Far North Holdings Limited

Renewal of discharge treated wastewater to land from industrial park Opua.

APP.007711.01

1

11/12/2024

Far North District Council

Renewal of discharge consent at Houhora Heads motor camp.

APP.046273.01

1

11/12/2024

BDO Pakihi Taitokerau Limited

Discharge consent for an on-site treatment system within 20 metres of an existing water supply
bore at 14 Mackie Place, Matapouri.

APP.040361.01

1

12/12/2024

Tiri Avocados Limited

S127 change to take groundwater from a bore to irrigate an orchard at Heath Rd, Waiharara

APP.046280.01

1

12/12/2024

Willowridge Developments Limited

Subdivision works at 39 Aucks Road, Russell

APP.037376.01

1

13/12/2024

CJ Harold

Replacement consent to discharge secondary treated domestic wastewater to land at 2319 Whananaki North Road,

APP.046285.01

1

16/12/2024

Te Putahi Developments Limited

Earthworks in a high risk flood area at 435-437 Kamo Road, Whangarei

APP.013827.01

1

17/12/2024

Firth Industries Division

Discharge contaminants to air from concrete manufacturing at Dargaville.

APP.046286.01

3

17/12/2024

Jannene Harker

Bore construction for domestic use at 126 Sweetwater Road, Awanui

APP.046287.01

3

17/12/2024

Strataform Limited

Bore construction for domestic and irrigation use at 2958 SH10, Mangonui

APP.002344.01

1

18/12/2024

Mangawhai Golf Club Inc

Replacement consent to take groundwater for irrigation of golf greens and club house supply at Mangawhai Golf Club, 221 Molewsorth Drive, Mangawhai

APP.008755.01

1

18/12/2024

Greg Smith Engineering (2012) Limited

Replacement consents for dry abrasive blasting operations at 2 Day Street, Dargaville

APP.011643.01

1

18/12/2024

Green Valley Estate Limited

Replacement consent to take groundwater for irrigation at 47 Proctor Road, Poroti

APP.041713.04

1

18/12/2024

Ballance Agri-Nutrients Limited

Replacement consent to discharge stormwater from a high risk industrial and trade premise into Te Waiiti Stream associated with a bulk fertiliser storage depot at 223 Kioreroa Road, Whangarei.

APP.046296.01

1

18/12/2024

C Ranwell

Discharges for a new wastewater system at 13C Emay Crescent, Pahi

APP.046303.01

1

19/12/2024

Northland Regional Council

Earthworks for flood protection at Russell Road, Punaruku

APP.006240.04

1

20/12/2024

Pigeon Mountain Trustee Company Ltd & Halcyon Days Trustee Company Ltd

Alteration to existing jetty facility structures in Waipiro Bay, Bay of Islands

APP.007063.01

1

20/12/2024

Rudolphs Limited

Replacement consent for abrasive blasting and spray painting at Lower Port Rd, Whangarei

APP.014345.01

1

20/12/2024

Reids Ruawai Transport Limited

Removal of overburden and extraction of rock from quarry at Whitcombes Road, Ruawai

APP.046304.01

1

20/12/2024

Northland Regional Council

Earthworks for flood protection works - Kaeo Stage II Flood Works, Kaeo River

APP.004191.01

1

23/12/2024

Hikurangi Golf Club Inc

Replacement consent to take surface water for irrigation of greens at 231 Marua Road, Hikurangi

APP.046307.01

1

23/12/2024

Northland Regional Council

Flood protection works Pairatahi River/Whangatane Spillway, Awanui/Kaitaia associated with the Awanui Flood Scheme upgrades

APP.046310.01

1

23/12/2024

Far North District Council

Works to improve operation of the Kawakawa Wastewater Treatment Plant at 5630 Paihia Road, Kawakawa

APP.046311.01

1

23/12/2024

Glenn Alexander Emery

Bore construction at 530 Matapouri Road, Tutukaka

APP.003330.01

1

31/12/2024

WK & KE Brown Family Trust & Wayne Keith Brown & Kathryn Elizabeth Brown

Replacement consent to take from a bore for irrigation at 26 Simons Road, Poroti

 

Table 2:       Consents Decisions Issued 1 July to 30 September 2024

IRIS ID

Consents Required

Description

Issue Date

AUT.046049.01.01

1

Misescu - Swing mooring in CMA at Wharf Road Mooring Zone at Whangaruru

1/10/2024

AUT.046069.01.01

3

IGNS Limited - Monitoring bore construction at Ari Ari Road, Pouto Peninsula

2/10/2024

AUT.046086.01.01

3

Holy - Bore for domestic and stock use at 1454 Purerua Road, Te Tii

3/10/2024

AUT.046103.01.01

3

Henwood - Bore construction for domestic use at 2884D SH10, Mangonui

3/10/2024

AUT.027140.01.02

1

Manawa Energy Limited - Discharge contaminants to air from the generation of electricity at Ruakaka.

3/10/2024

AUT.046031.01.01

4

Matatina Marae Trust - Earthworks for papakainga, Waipoua Settlement - NES FW

3/10/2024

AUT.046075.01.01

 

Greenstar Properties - Site development works at 10 Reservoir Rise, Whangarei

3/10/2024

AUT.046075.02.01

2

Greenstar Properties - SW diversion at 10 Reservoir Rise, Whangarei

3/10/2024

AUT.037936.02.02

2

Thornton:  Discharge contaminants to air at Manawaora Road, Russell

3/10/2024

AUT.012697.01.02

1

Busck Concrete Limited - Discharge to air at Fertilizer Road, Whangarei

8/10/2024

AUT.046105.01.01

1

Roberts - MM4 swing mooring 4272 in CMA at Te Uenga Bay Mooring Zone, Bay of Islands

9/10/2024

AUT.046107.01.01

3

Firth Industries Ltd - Bore construction at Moir Point Road, Mangawhai Heads

10/10/2024

AUT.046115.01.01

3

Meridian Energy Limited -  5 g-water monitoring bores at Port Marsden H/W and Marsden Pt Rd, Ruakaka

10/10/2024

AUT.046104.01.01

2

Allen & Hunt - Domestic discharge at 312 Waiotoi Road, Ngunguru

11/10/2024

AUT.046114.01.01

4

Paparoa Gospel Hall Trust - Earthworks in flood zone at Franklin Road, Paparoa

14/10/2024

AUT.042456.01.02

3

Tararua Wind Power Limited - s127 EW for construction of a wind farm at Maitahi Road, Mamaranui

16/10/2024

AUT.046129.01.01

2

Bidfood Ltd - Discharge commercial WW at Kahikatearoa Lane, Waipapa

16/10/2024

AUT.046106.01.01

3

Carrington Farms Jade LP - Bore construction at Matai Bay Rd, Karikari Peninsula

21/10/2024

AUT.045652.01.01

5

Thornton and Goodwin - Site development earthworks at Millington Rd, Whangarei

21/10/2024

AUT.046142.01.01

3

Waiharara Hall Society Inc - Bore for domestic use at 31 Kaimaumau Road, Waiharara

24/10/2024

AUT.045919.01.01

4

West Road Farms Ltd - Earthworks in flood zone at Spains Road, Awanui

25/10/2024

AUT.046130.01.01

3

Kaipara District Council - Carpark upgrade at corner of Alamar Cr and Olsen Ave, Mangawhai Heads

29/10/2024

AUT.046017.01.01

1

Z Energy Limited - Discharge of stormwater to land for station upgrade at 570 SH 10, Taipa

29/10/2024

AUT.046152.01.01

3

Groeneveld and Kameoka - Bore for domestic, stock and irrigation use at 3615 Horeke Road, Taheke

30/10/2024

AUT.046153.01.01

3

Gillett and Novoa - Bore construction for domestic and stock use at 545 Wiroa Road, Kerikeri

30/10/2024

AUT.046154.01.01

3

Horan - Bore for domestic use at 174A Houhora Heads Road, Pukenui

30/10/2024

AUT.046087.01.01

2

Hilton-Jones - Domestic discharge to land at 45 Landowners Lane, Tutukaka

30/10/2024

AUT.046122.01.01

2

Howell - Discharge domestic WW at 9 Christie Close, Pataua North

30/10/2024

AUT.007161.01.03

9

Mangawhai Harbour Restoration Society Inc. - Maintenance dredging in CMA of Mangawhai Harbour

31/10/2024

AUT.046172.01.01

3

Whangarei District Council - Earthworks to construct a flood pump at Rawhiti Street, Whangarei

1/11/2024

AUT.002478.01.05

1

Far North District Council - Change to a Groundwater take for public water supply of Kawakawa

5/11/2024

AUT.043352.01.01

2

Kauri Mountain Farms Ltd - Refuse disposal at Kauri Mountain Road, Taiharuru

6/11/2024

AUT.046013.01.01

2

Main Road Properties Ltd - Commercial WW system at SH 12, Maungaturoto

6/11/2024

AUT.046160.01.01

3

Cherrington - Bore construction at 3070 SH 1, Northern Aupouri

8/11/2024

AUT.045728.01.01

4

Leventis - Place a hard protection structure landward of MHWS at Taemaro Road, Hihi

8/11/2024

AUT.012944.01.02

4

Carpenter Investments Limited - Marine farm in CMA in Waikare Inlet, BoI (ex lease # 124)

12/11/2024

AUT.012995.01.02

4

Carpenter Investments Ltd - Marine farm in CMA in Waikare Inlet, BoI (ex lease # 345)

12/11/2024

AUT.045713.01.01

4

Te Puna Topu O Hokianga Trust - Low flow water take from Waihopai River for irrigation at Mitimiti

12/11/2024

AUT.046120.01.01

2

Ngati Manawa Marae Trustees - Discharge WW to land from marae facilities at West Coast Road, Panguru

13/11/2024

AUT.046128.01.01

5

Shepherd Property Development Ltd - Subdivision works at Cemetery Road, Maunu, Whangarei

14/11/2024

AUT.046165.01.01

5

Maunugold Ltd - Subdivision earthworks at 9-11 Cemetery Road, Maunu, Whangarei

15/11/2024

AUT.046176.02.01

2

Far North District Council - Waste transfer station at Enterprise St, Kaikohe

15/11/2024

AUT.009980.01.02

4

Whangarei District Council - Tutukaka WWTP - Discharge to water

15/11/2024

AUT.046209.01.01

2

Northpower Ltd - Works in and near wetlands at Ruawai and Te Kopuru (NES-FW)

18/11/2024

AUT.037602.01.02

2

Barnes - Discharge domestic WW to land at Marina Vista Heights, Tutukaka

18/11/2024

AUT.046182.01.01

3

Tararua Wind Power Ltd - Road improvement earthworks for Kaiwaikawe Wind Farm, Dargaville

19/11/2024

AUT.046217.01.01

10

Kaipara District Council - Hard protection structures above MHWS at Seaview Rd, Baylys Beach

20/11/2024

AUT.046108.01.01

5

Tararua Wind Power Ltd - Earthworks near wetlands for Kaiwaikawe Wind Farm,  Dargaville (NES-FW)

21/11/2024

AUT.007231.01.04

3

Kaipara District Council - Discharge WW to land at Glinks Gully WWTP, Rope Cr, Te Kopuru

22/11/2024

AUT.046183.01.01

4

Far North District Council - Earthworks to install WW main in flood zone at Bonnett Road, Kaitaia

25/11/2024

AUT.046218.01.01

2

Wairahi Tracks Charitable Trust - Earthworks in a wetland at Cove Road, Langs Beach - NES-FW

28/11/2024

AUT.046188.01.01

3

Slater and Dudley - Bore construction at 1487 SH 1, Okaihau

28/11/2024

AUT.046061.01.01

4

Mangawhai Hills Limited - Earthworks for Subdivision development at Cove Road, Mangawhai

29/11/2024

AUT.046177.01.01

1

Te Aupouri Commercial Development Ltd - Short term groundwater take at Salvation Rd, Pukenui

29/11/2024

AUT.045934.01.01

5

Twin Coast Highway LP - Onoing SW discharge for subdivision at Sands Road, Glenbervie

2/12/2024

AUT.046033.01.01

8

Robinia Investments Ltd - Jetty and floating pontoon in the CMA at Russell Wakapara Road, Russell

3/12/2024

AUT.046147.01.01

1

Far North District Council - Discharge to land at 149 Pukepoto Road, Kaitaia

3/12/2024

AUT.045770.01.01

3

Arco Group Ltd - Earthworks in flood hazard area at Saleyards Rd, Kauri, Whangarei

5/12/2024

AUT.046196.01.01

3

Lodestone Energy Ltd - Earthworks for a solar farm at Hoanga Rd and Danks Rd, Dargaville

5/12/2024

AUT.002312.01.05

1

Te Kihi Trust and others - Take groundwater take at Maungatapere

5/12/2024

AUT.046178.01.01

11

Spiers - Place and use culverts at Ladore Rd, Okaihau

6/12/2024

AUT.046010.01.01

2

Edwards & Milne - Jetty in CMA at 5 Moir St, Mangawhai

9/12/2024

AUT.046215.01.01

3

Pukenui School Board of Trustees - Bore for domestic and community supply at 35 Lamb Road, Pukenui

9/12/2024

AUT.046179.01.01

3

Far North District Council - Earthworks for stormwater network upgrade at Moerewa

9/12/2024

AUT.037337.01.02

2

Austin - Domestic on-site wastewater at Ngunguru Heights Rise, Ngunguru

9/12/2024

AUT.037581.01.02

2

Hylands Ancient Kauri Ltd - Commercial wastewater discharge at Kerikeri Road, Kerikeri

9/12/2024

AUT.045765.01.01

1

Norman - New swing mooring at Paroa Bay, Russell, Bay of Islands

10/12/2024

AUT.046205.01.01

3

The Salvation Army - Site development works at North Park Drive, Kaitaia

10/12/2024

AUT.046226.01.01

4

Vitali Farm Company Ltd - Earthworks within 10m of a natural wetland at 1509 Tinopai Road, Tinopai

10/12/2024

AUT.046227.01.01

4

Taurima Taumata Ltd - Bore construction for domestic use at McAdam Road, Waipu

12/12/2024

AUT.046237.01.01

2

Noro Investments - Bore construction for domestic and stock use at St Marys Road, Waipu

13/12/2024

AUT.046083.01.01

3

Summit Forests - Earthworks at Dutton Road, Peria

13/12/2024

AUT.046213.01.01

6

NZTA - Works in the bed of a stream Waiomio Stream, SH1, Waiomio

13/12/2024

AUT.046216.01.01

3

Franklin and Neilson - Bore construction at Edmonds Road, Kerikeri

16/12/2024

AUT.046184.01.01

3

Mangapuriri Estate Ltd - Works near a wetland at Browns Rd, Mangawhai (NES-FW)

16/12/2024

AUT.013576.01.04

5

MT Farms Pahi Ltd - Marine farm in CMA in Kirikiri Inlet, Kaipara Harbour (NES-MA)

17/12/2024

AUT.042368.01.02

4

Te Runanga O Whaingaroa - Subdivision works at Ash Grove Circle, Haruru

17/12/2024

AUT.004387.01.04

1

Mangawhai Beach Hideaway Park - Groundwater take for camping ground, Mangawhai Heads

17/12/2024

AUT.012962.01.04

4

Muriwhenua Incorporation - Marine farm in CMA in Parengarenga Harbour (Ex Lease # 177)

18/12/2024

AUT.046063.01.01

5

Heron Point Ltd - Site development earthworks at 47 Hihitahi Rise, Paihia (NES-FW)

18/12/2024

AUT.046208.01.01

4

Smyth - Site development works in flood zone at Windsor Way, Mangawhai

18/12/2024

AUT.013167.01.04

2

Oceans Resort Body Corporate 349622 - Groundwater takes at Oceans Resort at Marina Road, Tutukaka

20/12/2024

AUT.046236.01.01

1

Linder & Dawson - Take water from Awanui River for irrigation at Kaitaia

20/12/2024

AUT.038410.02.01

1

Sandstone Orchards Ltd Partnership - Take groundwater at Srhoj Road, Waiharara

23/12/2024

AUT.043505.01.01

1

Robert Campbell Trust - Groundwater take for irrigation at Big Flat Rd, Waiharara

23/12/2024

 

 

Attachments/Ngā tapirihanga

Nil

 

 


Audit and Risk Committee                                                                               item: 6.6

18 February 2025

 

TITLE:

RMA Compliance, Monitoring and Enforcement Framework

From:

Colin Dall, Pou Whakaritenga - Group Manager Regulatory Services

Authorised by Group Manager/s:

Colin Dall, Pou Whakaritenga - Group Manager Regulatory Services, on 11 February 2025

 

Executive summary/Whakarāpopototanga

A draft council Resource Management Act (RMA) compliance, monitoring and enforcement framework was presented to the committee at its 29 May 2024 meeting to consider and provide feedback on.  Since then, staff have further developed and revised the framework.

 

A copy of the revised framework is attached to this report.   The framework will provide greater clarity and transparency of council’s overall approach to RMA compliance, monitoring and enforcement (CME).  This report seeks the committee’s endorsement of the framework.

 

Should the committee endorse the revised framework, it will be presented to the council at its March or April meeting for its consideration and approval.

 

Recommendation(s)

1.        That the report ‘RMA Compliance, Monitoring and Enforcement Framework’ by Colin Dall, Pou Whakaritenga - Group Manager Regulatory Services and dated 11 February 2025, be received.

2.        That the committee recommends to council that it approves the RMA Compliance, Monitoring and Enforcement Framework attached to this report.

Options

No.

Option

Advantages

Disadvantages

1

Status quo – no single document setting out the council’s overall approach to fulfilling its RMA compliance, monitoring and enforcement functions.

 

None.

Lack of clarity and transparency in council’s overall approach to to fulfilling its RMA CME functions.

2

Approved documented framework setting out the council’s overall approach to fulfilling its RMA CME functions.

Council’s approach to RMA CME clear and transparent.

 

 

None.

 

The staff’s recommended option is Option 2.

 

Considerations

Being an administrative matter (setting out existing practices, policies and protocols in a single document), Climate and Environmental impacts, and Financial implications are not applicable.

 

1.    Community views and Māori impact statement

The community and tangata whenua are often interested in how the council fulfils its RMA compliance, monitoring and enforcement functions. Setting out our overall approach to this in a single document will make this clearer and more transparent to everyone.

2.    Implementation issues

Both options are easy to implement.

 

3.    Significance and engagement

 

4.    Policy, risk management and legislative compliance

Both options presented are legislatively compliant.

 

Background/Tuhinga

Council currently undertakes its Resource Management Act compliance, monitoring and enforcement functions in accordance with the requirements of the Act, national and regional sector guidelines, and the council’s Compliance, Monitoring and Enforcement Strategy (CMES).  How council fulfils these functions is set out in a range of documents including manuals, activity management plans, procedures and protocols.  Staff have set out our overall approach in a single document called the “Northland Regional Council RMA Compliance, Monitoring and Enforcement Framework” to provide greater clarity and transparency of this approach.

 

Attachments/Ngā tapirihanga

Attachment 1: NRC RMA CMA Framework

Attachment 2: MfE Best Practice Guidelines for RMA CME

Attachment 3: Controller & Auditor General's Directive on Unannounced Monitoring Visits  

 

 


Audit and Risk Committee  ITEM: 6.6

18 February 2025Attachment 1








 


Audit and Risk Committee  ITEM: 6.6

18 February 2025Attachment 2

A river flowing through a forest

Description automatically generated

A document with text on it

Description automatically generated

A paper with text on it

Description automatically generated

A paper with text on it

Description automatically generated

A white paper with black text

Description automatically generated

A white paper with black text

Description automatically generated

A close-up of a letter

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A white background with black dots

Description automatically generated

A close-up of a document

Description automatically generated

A white and blue text with black text

Description automatically generated


A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A white paper with black text

Description automatically generated

A document with text on it

Description automatically generated

A screenshot of a document

Description automatically generated

A close-up of a document

Description automatically generated


A document with text on it

Description automatically generated


A close-up of a document

Description automatically generated



A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A paper with text on it

Description automatically generated



A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated


A document with text on it

Description automatically generated


A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated


A close-up of a document

Description automatically generated

A document with black text

Description automatically generated


A close-up of a document

Description automatically generated


A document with text on it

Description automatically generated


A close-up of a paper

Description automatically generated

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated


A close-up of a document

Description automatically generated




A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated




A document with text on it

Description automatically generated


A close-up of a paper

Description automatically generated

A document with text on it

Description automatically generated

A screenshot of a document

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a paper

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a paper

Description automatically generated

A document with text and colorful text

Description automatically generated with medium confidence

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A diagram of a company

Description automatically generated with medium confidence

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A letter of a warning

Description automatically generated with medium confidence

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A paper with text on it

Description automatically generated

A paper with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A screenshot of a computer

Description automatically generated

A document with text on it

Description automatically generated

A page of a document

Description automatically generated


A diagram of a flowchart

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A document with text and colors

Description automatically generated with medium confidence

A document with text on it

Description automatically generated

A screenshot of a document

Description automatically generated

A close-up of a document

Description automatically generated


A close-up of a document

Description automatically generated

A close-up of a document

Description automatically generated

A document with text and images

Description automatically generated

A close-up of a document

Description automatically generated

A document with text on it

Description automatically generated

A document with text on it

Description automatically generated

 


Audit and Risk Committee  ITEM: 6.6

18 February 2025Attachment 3


 


Audit and Risk Committee                                                                               item: 6.7

18 February 2025

 

 

TITLE:

Financial Report to 31 January 2025

From:

Taka Skipwith, Financial Accountant

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 11 February 2025

 

Whakarāpopototanga / Executive summary

This report details the YTD financial results on 31 January 2025. The council has achieved a YTD surplus of $3.9m after transfers to and from reserves, which is $1.0m higher than the Adopted (Original) budgeted surplus of $2.9m. This report has been submitted to the draft agenda for council meeting to be held 25 February 2025 and may be amended if required.

 

Ngā mahi tūtohutia / Recommendation(s)

1.    That the report ‘Financial Report to 31 January 2025’ by Taka Skipwith, Financial Accountant and dated 11 February 2025, be received.

 

 

Background/Tuhinga 

The operating surplus, before transfers to and from reserves, for the YTD period ending 31 January 2025, is $9.1m, exceeding the adopted budget of $8.8m by $306k, refer to Table 1.

Table 1

 

The main contributing factors for the YTD surplus are.

 

YTD Operating Revenue (table 4) deficit of ($798k) which is 1.5% of the budget and predominantly due to:

·    Higher than planned gains from managed investments funds of $1.93m, which is 74.7% higher than budgeted.  Refer to Table 3.

Actual fund gains YTD is $4.5m against a budget of $2.6m,

Due to Council’s YTD favourable surplus, the fund gains were not required for general funding as budgeted.  Therefore, fund gains of $3.6m were transferred to special reserves verses the budgeted transfer of $649k.

·    Higher than planned interest income of $510k, and

·    Unplanned gain on sale of carbon credits of $218k

·    Higher than planned user fees and sundry income of $149k mainly from other parties for the Strategic review.

·    Lower than planned grants and subsidies of ($3.4m) and lower than planned dividend of ($388k)

 

YTD Operational Expenditure (table 5) favourable surplus of $1.1m which is 2.4% of the budget, predominantly due to:

·    Lower than budgeted expenditure for Environmental Services of $840k for

Consultancy and Contractors of $165k

Field operations of $84k

Net Salary Savings across the group of $492k

·    Lower than budged expenditure for Biosecurity of $484k for

Consultancy and Professional fees of $124k

Net Salary Savings across the group of $330k

 

 

Net Salary savings across all of Council for YTD January 2025 is $1.1m, due to the vacancies across Council, partially offset by annual leave owed to staff, redirected salaries, and other employment costs.  This month $30k of Salary savings was approved to be redirected to contractor costs for the strategic delivery refresh.

Table 2


 

 

Reserve Movements

For the year to date there has been a net transfer to reserves of $5.1m compared to a budgeted net transfer to reserves of $5.8m. The variance of $711k, is due mainly to transfers to the Rivers and Land reserves that are lower than budgeted of ($3.1m), and higher than budgeted transfers to reserves associated with managed funds of $2.8m.   Additional reserves movements listed in Table 6 contribute to this variance.

 

Capital Expenditure

Capital expenditure YTD amounts to $3.7m and is $2.0m lower than the corresponding budget of $5.7m at this stage of the year.  This is due mainly to

·    Tsunami network upgrade work of ($1.3m) higher than budget which will be supported by TLA contributions.

·    Joint emergency co-ordination centre behind budget by $1.1m.

·    Multiple river projects behind budget of $1.5m due to delayed works.

·    Hydrology and Water quality equipment programme behind budget by $176k,

·    Council property construction and improvements behind budget by $381k.

 

Table 3


 

Table 4

Table 5

 

Table 6

 

 

 

 

Attachments/Ngā tapirihanga

Nil

 

 


Audit and Risk Committee                                                                               item: 6.8

18 February 2025

 

TITLE:

Insurance Update

From:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services

Authorised by Group Manager/s:

Bruce Howse, Pou Taumatua – Group Manager Corporate Services, on 07 February 2025

 

Whakarāpopototanga / Executive summary

Council’s total insurance premium for 2024/25 is $772,732, this represents a 5.34% increase over the 2023/24 total insurance premium of $733,543.

 

A summary of council’s insurance renewals for 2024/25 is attached.  This summary includes comments on significant changes and drivers in the increase in premium values.

 

The more material premium increases relate to:

·    Material damage ($10,331 premium increase) – driven by an increase in value for Tsunami Siren’s in storage and Hydrology sites.  NRC recovers 75% of the premium from tenants across all rental properties.

·    Professional indemnity ($12,578 premium increase).

·    Marine Hull ($10,132 premium increase) – driven by the new Waikare II replacement value

 

 

Ngā mahi tūtohutia / Recommendation

That the report ‘Insurance Update’ by Bruce Howse, Pou Taumatua – Group Manager Corporate Services and dated 31 January 2025, be received.

 

Background/Tuhinga

Not applicable.

 

Attachments/Ngā tapirihanga

Attachment 1: Insurance Summary 2024-2025  

 

 


Audit and Risk Committee  ITEM: 6.8

18 February 2025Attachment 1


  

 


Audit and Risk Committee                                                                                                     ITEM: 7.0

18 February 2025

 

TITLE:

Business with the Public Excluded

 

Whakarāpopototanga / Executive Summary

The purpose of this report is to recommend that the public be excluded from the proceedings of this meeting to consider the confidential matters detailed below for the reasons given.

Ngā mahi tūtohutia / Recommendations

1.              That the public be excluded from the proceedings of this meeting to consider confidential matters.

2.              That the general subject of the matters to be considered whilst the public is excluded, the reasons for passing this resolution in relation to this matter, and the specific grounds under the Local Government Official Information and Meetings Act 1987 for the passing of this resolution, are as follows:

Item No.

Item Issue

Reasons/Grounds

7.1

Confirmation of Confidential Minutes - 18 November 2024

The public conduct of the proceedings would be likely to result in disclosure of information, the withholding of which is necessary to protect information where the making available of the information would be likely unreasonably to prejudice the commercial position of the person who supplied or who is the subject of the information s7(2)(b)(ii).

7.2

Risk Management Activity Update

The public conduct of the proceedings would be likely to result in disclosure of information, the withholding of which is necessary to protect information where the making available of the information would be likely unreasonably to prejudice the commercial position of the person who supplied or who is the subject of the information s7(2)(b)(ii).

7.3

Report on Litigation and Enforcement 01 October - 31 December 2024

The public conduct of the proceedings would be likely to result in disclosure of information, the withholding of which is necessary to protect the privacy of natural persons, including that of deceased natural persons s7(2)(a).

3.              That the Independent Advisors be permitted to stay during business with the public excluded.

Considerations

1.    Significance and Engagement

This is a procedural matter required by law. Hence when assessed against council policy is deemed to be of low significance.

2.    Policy and Legislative Compliance

The report complies with the provisions to exclude the public from the whole or any part of the proceedings of any meeting as detailed in sections 47 and 48 of the Local Government Official Information Act 1987.

3.    Other Considerations

Being a purely administrative matter; Climate Impact, Environmental Impact, Community Views, Māori Impact Statement, Financial Implications, and Implementation Issues are not applicable.